Axis’ Mechanical & Electrical Division replaced all existing boilers at a prestigious Grade A office building
New modular boilers
Isolation of existing system
Draining, stripping and removing cast iron sectional boilers
Installation of control panel
Lining and replacement of flue sections
New Building Management System
Project Details
Our Mechanical and Electrical division carried out a commercial boiler installation on behalf of our client, The Crown Estate. The works took place at a prestigious Grade A office building at 16 St James’s Street, in London.
Our team began works in the basement plant room, we drained and stripped the existing cast iron sectional boilers and associated shunt pumps. The primary pipework and Building Management System Panel (BMS) controls were also removed. As part of the commercial boiler installation, new modular boilers were added alongside a new pump set serving the primary circuit. Back-end protection, pipework, low loss header, valves, controls and ancillaries were also fitted.
Our team installed a new pressurisation unit, dosing pot, and expansion vessel with BMS controls to connect with the existing system. We added inset flue lining where required, along with replacement sections at reception level and in the basement plant room.
Project partnership
As a result of our successful partnership with The Crown Estate, our M&E team were invited back for a second project. Our team was tasked with the installation of bespoke lighting and access systems in the reception area at 16 St James’s. This award-winning property is mixed-use; it houses a restaurant, office space and residential apartments. It is located in one of London’s most prestigious postcodes near to the Ritz hotel.