The facade of a large building undergoing cladding remediation works, completely covered in scaffolding and blue safety netting.
Home | Case study | Cladding Remediation Works

Cladding Remediation Works

Sector

Social Housing

Location

London

Service

Building Compliance

Peabody’s Bristow Court is a 7-storey block containing 21 residential flats arranged over four floors on Triangle Road in Hackney East London. There are six flats on each of the first, second and third floors and three on the top floor. The high-end apartments are of mixed tenure and fully occupied, in the main, by professional leaseholders. The ground floor comprises commercial units.

Peabody

Axis delivers cladding remediation works to the value of £3.5 million for Peabody.

Project Details

Peabody appointed Axis for a two-stage JCT** intermediate contract with contractor’s design portion for the removal of existing non-compliant HPL cladding and renewal with new Rockpanel rainscreen cladding system.

Axis continued the cladding remediation works from a previous contractor who had stripped some of the existing cladding so there were issues of damp in some of the apartments. Therefore, prior to works commencing, we conducted pre-condition surveys to all properties to inspect damp and condensation issues; check all windows and gas installations as well as assess any vulnerabilities of residents. We also updated our contacts list to effectively communicate with residents throughout the works.

The team erected scaffolding for the duration of the cladding remediation works. The scaffold was fully alarmed with Robo Watch and had underlighting for full visibility and security. When the scaffold was erected, we conducted pull-out tests in preparation for removing existing cladding.

A railway line, which runs at the back of the block of flats, had to be closed for Axis to erect our scaffolding. We submitted a scaffold design to Network Rail and were able to continue works to the front of the building meanwhile.

To the front elevation the team replaced the cladding on the balconies and soffits with non-combustible cladding in a wood effect in keeping with existing style. To the rear elevation Axis removed existing cladding and installed Wetherby insulation system and Rock panel cladding.

Axis replaced cladding on the balconies with non-combustible cladding in a wood effect in keeping with existing style, including reinstated cladding and insulation to the sofitts on the balcony.

Care of our Residents

We kept residents fully informed prior to works commencing and throughout the duration of the works. COVID-19 restricted our usual Open-Door policy in our Site Office directly in front of the main entrance to Bristow Court, so we provided updates via Zoom meetings and regular announcements in communal areas and hand delivered Newsletters.

We were able to conduct the cladding works to the exterior of the building without accessing the interiors of the apartments so disruption to residents was kept to a minimum. Regular communications were additionally sent to residents about scaffold security.

Axis and Peabody always prioritised the safety of residents and, as these works were carried out during the Covid-19 pandemic, Axis staff wore appropriate PPE equipment, conducted hygiene and safety checks before entering residents’ homes; carried out regular cleaning and kept non-essential personal contact to a minimum. Axis followed government guidelines throughout the works.

Further works:

The team was contracted to do some extra on the project: roof works included fitting a handrail; and we also made good after works on the boilers were completed.

Find more of our housing projects, here.

Specifications

  • Pre-condition surveys
  • Removal and replacement of existing cladding
  • Scaffolding
  • Pull out tests
  • 7-storey block
  • High-end apartments

Planned repairs services

Looking for more information about Axis’ repair services? Click below to find out more.

020 756 42100
info@axiseurope.com

Please enter your first name

Please enter your surname

Please enter a valid email address

Please add description of enquiry

Please agree to the terms*

Thank you! Your form has been successfully submitted. Someone will be in touch with you soon.

Error sending form.

View or share this case study

Download

You may also be interested in...

Notting Hill Genesis – Castletown Road, West Kensington

These works form part of Axis’s refurbishment programme for Notting Hill Genesis at Castletown Road, focused on improving accessibility, comfort...

Overhead shot of three high rise buildings covered in scaffolding

Lewisham Park Towers – Major Investment Programme

Axis delivered a comprehensive £20 million Major Investment Programme across three 17-storey tower blocks for L&Q Housing Association.

Damp & Mould Remediation for Dudley Metropolitan Borough Council

Axis delivers damp and mould remediation for Dudley MBC across 21,000 homes, improving living conditions and achieving 100% compliance.

CLC employee scanning a wall for damp and mould

Riverside Damp and Mould Remediation Programme

Axis CLC delivers a specialist damp and mould remediation programme for The Riverside Group in West Bromwich. The team provides...

Rosehill Court – Full Refurbishment

£3.1m refurbishment of 59 flats and 10 commercial units at Rosehill Court, Sutton, delivered over 19 months.

The Honourable Society of Gray’s Inn, Gray’s Inn Square

These works form part of Axis's 10+ year contract with The Honourable Society of Gray’s Inn.

Roof and Solar PV Replacement

A £1.4 million roof retrofit and solar PV installation enhancing energy efficiency, sustainability, and overall building performance

Full Refurbishment

Our full bespoke refurbishment of the Metropolitan Police Vehicle Workshops was completed in 6 months to the satisfaction of our...

An aerial photo showing the clear difference between a newly replaced, dark brown tiled roof (left) and an old, weathered grey tiled roof (right) on a brick terraced house, demonstrating the result of roof renewal and repair.

Roof Repairs and Maintenance Works for MHS

Reactive Roof Repairs and Maintenance Works programme weatherproofs and futureproofs MHS' residential dwellings in Kent

premier inn hotel room with bed tv dinning table open wardrobe mirror entrance to ensuite

Premier Inn – Wirral Met College

We partnered with Wirral Met College to deliver a fully functioning hotel training facility - transforming a 150 sq m...

Harrogate and District NHS Foundation Trust

We delivered a £1.4m multi-site refurbishment for Harrogate and District NHS Foundation Trust transforming clinical and support spaces across Grove...

Midlands Partnership NHS Foundation Trust

We upgraded or replacement over 400 fire doors at the inpatient Mental Health Services and Old Age Psychiatry facility.

A close-up of newly installed black solar PV panels on a tiled roof, showing the reflective, crystalline surface and the clean installation edge over the brown roof tiles.

Solar Panels Eastlight Community Homes

Our 3-week Solar PV installation programme brings energy efficiency and cost saving benefits to Eastlight residents

Fire door close up of sign that says Fire Door Keep Shut

VIVO Defence Services – Dorset & Wiltshire Fire and Rescue

With VIVO Defence we successfully completed fire safety works to five buildings including 277 fire door set replacements.

National Property and Construction Management Consultancy team overseeing large-scale housing projects across the UK.

Planned Cyclical Maintenance

Delivering planned cyclical maintenance on multiple properties in West London for Notting Hill Genesis. This improved energy efficiency.

Alnwick District Playhouse Trust

We extended the roofs at all 36 properties to allow for extra 150 millimetres of EWI.

A view of the multi-storey brick care home from its communal garden, showing the new conservatory and peaceful patio area with benches.

Communal Repairs and Decoration Works

Delivering communal repairs and decoration, enhancing communal areas, guestrooms and a garden for Notting Hill Genesis.

Construction workers in high-visibility vests and hard hats stand on a large, newly boarded timber roof structure under an extensive temporary roof scaffolding system, indicating major roof renewal programme work.

Roof Renewal Programme

Axis' major Roof Renewal programme over 20 weeks for Notting Hill Genesis waterproofed the property and increased thermal efficiency

A modern refurbished office corridor featuring black-framed Crittall-style glass walls and contemporary circular LED pendant lights, which are reflected in the glass.

Re-modelling and refurbishment of office space

Axis' extensive refurbishment project creates modern, practical working space in heritage building for The Honourable Society of Gray’s Inn

The historic Grade II listed Thames Tunnel Mills building, a former warehouse converted to residences, viewed from the riverside on a sunny day.

Grade II residential building upgrade

Axis delivered this Grade II residential building upgrade at Thames Tunnel Mills on the banks of the Thames for L&Q